GOLD NEWS

MAY TAKE TIME

SA gold and platinum majors ramping up

As South African mines get improved power supply, one major gold company says it will take it one to two weeks to reach optimum production at 90% power supply again.

Author: Tessa Kruger
Posted:  Saturday , 02 Feb 2008

JOHANNESBURG - 

South African mining companies were building up to optimum production levels at 90% of power supply yesterday as Eskom finally delivered on its supply commitment.

Anglo Platinum (JSE:AMS) was "building up" to resume concentrating refining and smelting activities, while Gold Fields was in the build-up phase to achieve optimum production at the reduced power level.

Gold Fields (JSE:GFI) spokesperson Reidwaan Wookay, told Mineweb that the organisation would naturally not run at full production on 90% of its average power use, but it was building up to reach sustained production.

Wookay said it would take Gold Fields about a week to two weeks to reach a sustainable production level after its mines were "switched off" a week ago. Mines across the South African mining industry came to a standstill last Friday as Eskom couldn't guarantee uninterrupted power supply and requested some to run at emergency power levels.

He said that Gold Fields was in constant dialogue with the power provider and was still pressing for continuous power supply. The power utility did previously commit to give mines at least four hours warning before power supply was shut down or reduced.

Gold Fields appeared to be alarmed after it received only 80% power supply Thursday as it issued a statement that said it wanted Eskom to guarantee it 90% supply. Supply was increased to 90% Thursday night and remained at this level Friday.

Anglo Platinum spokesperson Trevor Raymond said the company was mining underground at 100% capacity at the moment and would start concentrating, refining and smelting next week.

He said last week's events of power cuts "precipitated the crises"; the mining industry and Eskom has decided how to address it and now it was up to the two parties to make it work. Raymond referred to the industry's agreement to use 10% less power than its average power use.

Spokesperson for the Chamber of Mines Jabu Maphalala said 90% of power supply had been restored to the industry. The Chamber worked with Eskom to reach this agreement and was standing on Eskom's commitment to sustain this level of supply.

SUBSCRIBE to Mineweb.com's free daily newsletter now.

SHARE THIS ARTICLE

Print icon  Print story   Email icon   Email story    Subscribe icon  Subscribe to free newsletter  

Related Links

ARTILCES:  Price of darkness – Mining exec details the costs of shutdown to SA 
South African gold and platinum mines still at heavily reduced production rates 
South African mines to resume production this week 
OTHER PAGES:  GOLD NEWS PLATINUM GROUP METALS AFRICA
BackBack
INVESTOR HUB: Gold


View more charts 


TOP STORIES

RECORD COPPER, ZINC PRODUCTION

Teck comes roaring back in 2009 with second highest earnings ever

Tuesday , 09 Feb 2010
Strong base metals prices and record metals production last year gave Teck Resources a welcome infusion of profits in 2009, which enabled Canada's largest miner to report its second highest net earnings ever.
More 

FAST NEWS

PLANS TO CUT 170 JOBS

Outotec Q4 earnings miss forecast