|
PLATINUM GROUP METALS
|
|
INDUSTRIAL METALS
|
|
GOLD NEWS
|
|
DIAMOND & GEMS
|
|
JUNIOR MINING
|
|
MINING FINANCE
|
Western Utilities has completed a Definitive Feasibility study on urgent treatment of Acid Mine Drainage in South Africa's Wits Basin.
Author: Russell & Assoc.JOHANNESBURG -
Watermark Global Plc wholly-owned subsidiary Western Utilities Corporation (WUC) - working against the clock to implement its solution to the looming threat of far-reaching environmental damage posed by underground acid mine drainage (AMD) in the Witwatersrand (Wits) Basin - has announced completion of its Definitive Feasibility Study (DFS).
WUC CEO Jaco Schoeman says the DFS validates the viability of WUC's project, which envisages the construction of a bespoke water treatment plant, using South African-developed technology. The planned plant will treat 155 Ml of Wits Basin AMD daily to produce 67 Ml of industrial water and 88 Ml of drinking water.
The total capital cost of the project of R1.5 billion (US$195.5 million) will be raised by Watermark Global Plc via a combination of debt and equity, to be finalised by March 2010. This capital amount excludes R500 million worth of existing infrastructure already committed by interested and affected mining company shareholders of Western Basin Environmental Corporation (WBEC), Central Basin Environmental Corporation (CBEC) and Eastern Basin Environmental Corporation (EBEC), all Section 21 companies.
Of the R1.5 billion capital requirement, the major proportion - some R968 million - is required for construction of the treatment plant at Boksburg on the East Rand. The AMD collection system will absorb some R275 million and the treated water distribution system a further R225 million.
Schoeman says the project's tight timeline - designed specifically to head off the threat of a major decant of AMD on surface accurately pinpointed by consultants Golder Associates to occur in December 2011 - is already running nearly six weeks behind schedule due to a delay by the Gauteng Department of Agriculture and Rural Development (GDARD) in approving WUC's Final Scoping Report. Approval, expected on 28 September, is now expected by the end of this week.
A six-week delay on the ‘front end' of the project will have a knock-on effect, Schoeman says, which could delay the commissioning phase, originally planned to start in January 2011, by at least four months. Construction - originally scheduled to begin in January 2010 - is now unlikely to start before the second quarter of 2010. Any further delays could result in the race against the predicted December 2011 AMD decant being lost.
Meanwhile, Schoeman says, WUC is currently pushing ahead with negotiations on an offtake agreement with Rand Water for the drinking water it plans to produce. A full financial analysis, including expected rates or return, will be released once negotiations with Rand Water have been concluded.
In addition, WUC expects to finalise negotiations with prospective black economic empowerment (BEE) partners shortly, and this is expected to accelerate the project's integrated regulatory process (IRP), which - critically - includes submission and approval of its Environmental Impact Assessment and its application for an integrated water use licence (IWULA).
Disclaimer
MINEWEB is an interactive publication, with rolling deadlines through each day, commencing in the Sydney morning, and concluding, 24 hours later, in the Vancouver evening. If you believe your side of an issue deserves inclusion, but has failed to meet one of our deadlines, you are invited to notify the Editor in Chief in Johannesburg, and we will include you in our editing and expanding on our stories. Email him at alechogg@gmail.com
|
|
||||||
|
|
|
|||||



